Groundworks Cost Calculator (UK)

Price a foundation trench or a site dig the way a groundworker does: machine dig per m³, C25 concrete with 7% waste, and grab loads with 30% soil bulking — as a low–high range, ex or inc VAT.

What are you pricing?
  • m
  • ft
  • yd
  • m
  • cm
  • mm
  • ft
  • in
  • m
  • cm
  • mm
  • ft
  • in
  • Trench fill
  • Strip (300 mm concrete)
  • Dig only (no concrete)
  • Excluding VAT (trade quotes)
  • Including 20% VAT
Ranges use published 2026 UK guide rates — machine dig £85–£125/m³, C25 ready-mix £110–£139/m³, 6-wheel grab £310–£360/load (ex VAT). Real quotes vary with soil, access and region; London runs 15–25% higher.

Foundation trench estimate

Estimated cost
Excavation
Concrete
Muck-away
Dig volume
How it’s calculated

Quick Answer

UK groundworks are priced from three components: machine excavation at £85–£125 per m³, C25 ready-mix concrete at £110–£139 per m³ (ex VAT, plus about 7% ordering waste), and muck-away at £310–£360 per 6-wheel grab load — with dug soil bulking up around 30% before it is carted off. A typical 10 m × 0.6 m × 1 m trench-fill foundation works out at roughly £1,420–£1,870 excluding VAT.

UK groundworks cost breakdown — foundation trench cross-section with dig and concrete rates per cubic metre and a grab lorry muck-away load price with 30 percent soil bulking
UK groundworks priced by component: the trench volume sets the machine-dig cost, the concrete fill is ordered with 7% waste, and the spoil bulks up ~30% before the grab lorry carts it away. This groundworks cost calculator builds a low–high range from published 2026 rates.

The 2026 UK Rates This Calculator Uses

Every figure in this groundworks cost calculator comes from a published UK price guide — no invented rates. The estimate is a low–high range because that is how the guides themselves quote; your soil, access and postcode decide where you land in it.

Component2026 guide rate (ex VAT)Notes
Machine excavation£85 – £125 per m³hand dig runs £85 – £145 per m³
Ready-mix concrete (C25)£110 – £139 per m³+ delivery £50 – £200; London 15–25% higher
Muck-away, 6-wheel grab£310 – £360 per load12–14 tonnes ≈ 8–9 m³ of bulked soil
Muck-away, 8-wheel grab£370 – £420 per load16–18 tonnes, for bigger digs
Groundworker labour£180 – £320 per dayup to £440/day in London
Line pump hire£275 – £450 per daywhere the truck can’t reach the trench

How the Estimate Is Built

Groundworkers price a trench from its volume, and so does this tool. Concrete gets a 7% ordering allowance, and dug soil bulks up about 30% the moment it leaves the ground — which is why a “small” dig fills more grab lorries than you expect.

Dig volume = length × width × depth.
Dig cost = volume × £85–£125. Concrete = length × width × concrete depth × 1.07 waste × £110–£139.
Muck-away = volume × 1.3 bulking ÷ 8.5 m³ per 6-wheeler, rounded up to whole loads × £310–£360.

The concrete depth follows the foundation type: trench fill is poured to about 150 mm below ground level (fast, concrete-hungry), a strip footing takes roughly 300 mm of concrete in the trench bottom with masonry built up to damp-proof course on top (the bricklaying is not in this estimate), and dig only suits service or drainage trenches with no concrete at all.

Foundation Cost per Metre: How the Guide Bands Compare

Cost guides quote foundations per linear metre, but their bands disagree because each one bundles different things. For a standard 0.6 m wide, 1.0 m deep trench, this calculator’s component math lands at about £140–£185 per metre for trench fill and £100–£135 per metre for strip (dig + concrete + muck-away, ex VAT) — inside the published bands:

GuideStrip foundationsTrench fill
Checkatrade (machine dig)£95 – £115 /m£130 – £160 /m
Checkatrade (hand dig)£170 – £220 /m£220 – £280 /m
2 Brothers (domestic, all-in)£130 – £200 /m£160 – £240 /m
This calculator (components)≈ £100 – £135 /m≈ £140 – £185 /m

Strip looks cheaper per metre only because the masonry that must be built up inside the trench is priced separately. On difficult ground or where labour is dear, trench fill often wins overall — that is exactly the trade-off the two foundation-type options let you compare.

How to Use the Groundworks Cost Calculator

  1. Pick Foundation trench or Area dig

    Use Foundation trench for footings and drainage runs, or Area dig for stripping ground under a slab, driveway or patio.

  2. Trench mode: enter the run and pick a type

    Add up every side of the trench for the length (a 4 m × 3 m extension dug on three sides is 10 m), keep the standard 0.6 m width and 1.0 m depth unless you know better, then choose trench fill, strip or dig only. Use the picker beside each field to type in metres, centimetres, millimetres, feet or inches — 600 mm and 0.6 m give the same answer.

  3. Area mode: enter the footprint and depth

    Type the area in square metres, square feet or square yards, and how deep the ground gets stripped — driveways and patios usually come off at 0.2–0.3 m (200–300 mm). If you only have lengths, the square metre calculator turns them into m², ft² or yd² first.

  4. Choose ex or inc VAT

    Guide rates are quoted excluding VAT. If you are a homeowner paying a VAT-registered contractor, switch to “Including 20% VAT” to see the real bill.

  5. Read the range and the working

    The result card shows the total low–high range, the split between dig, concrete and muck-away, and every calculation line — so you can sanity-check any quote against it.

Groundworks Cost Examples

Every row is reproducible in the calculator above (machine dig, ex VAT unless stated):

JobDig volumeConcreteGrab loadsEstimated range
Extension trench fill, 10 × 0.6 × 1.0 m6 m³5.5 m³1£1,420 – £1,869
Same job, including 20% VAT6 m³5.5 m³1£1,704 – £2,242
House strip footings, 80 × 0.6 × 1.0 m48 m³15.4 m³8£8,255 – £11,022
Drainage trench (dig only), 15 × 0.45 × 0.6 m4.1 m³1£654 – £866
Garage base area dig, 30 m² × 0.3 m9 m³2£1,385 – £1,845

For scale: a published full-service worked example for an 80-metre strip-foundation dig on a 4-bed house — including labour, pump hire and building control — lands at £17,500–£21,000. The gap between that and the £8,255–£11,022 component estimate above is the labour beyond the dig, the masonry, the pump and the fees: exactly the extras listed below.

VAT and What the Estimate Leaves Out

The VAT trap: grab-lorry and ready-mix prices are published excluding VAT, and many groundworker quotes follow suit. A homeowner comparing an ex-VAT estimate against an inc-VAT quote sees a phantom 20% difference — switch the calculator’s VAT picker before you judge any quote.

Not included: concrete delivery (£50–£200) and pump hire (£275–£450/day for a line pump), building control fees (£300–£1,000), masonry above strip footings, reinforcement, drainage pipework, sub-base and slabs, and labour beyond the machine dig. Ground surprises — running sand, roots, old footings, high water table — move real quotes, and London runs 15–25% above the national bands.

Frequently Asked Questions

Priced from components: machine excavation £85–£125 per m³, C25 ready-mix £110–£139 per m³ and muck-away £310–£360 per 6-wheel grab load, all ex VAT. A typical 10 m × 0.6 m × 1 m trench-fill foundation comes to roughly £1,420–£1,870 ex VAT; a full 80 m house-foundation package with labour, pump and fees can reach £17,500–£21,000.

Published 2026 bands for a standard 0.6 m wide trench: strip foundations £95–£115 per metre machine-dug (£170–£220 hand-dug) and trench fill £130–£160 per metre machine-dug (£220–£280 hand-dug), with all-in domestic quotes running to £200–£240 per metre. This calculator builds the same number from dig volume, concrete and muck-away so you can see the split.

Dug soil bulks up about 30%, and a 6-wheel grab lorry takes 12–14 tonnes — around 8–9 m³ of bulked spoil. So divide your dig volume × 1.3 by about 8.5 and round up: a 6 m³ trench is one load, a 48 m³ house dig is eight. At £310–£360 per load, under-counting loads is the most common hole in a DIY groundworks budget.

Often not — grab hire and ready-mix guide prices are published excluding VAT, and VAT-registered contractors usually quote ex VAT too. Homeowners pay the standard 20% on top, so a £10,000 quote really costs £12,000. The calculator’s VAT picker shows both versions of the same estimate.

Strip foundations pour about 300 mm of concrete in the trench bottom and build masonry up to damp-proof course — less concrete, more bricklaying. Trench fill pours concrete to about 150 mm below ground level — much more concrete, almost no below-ground masonry, and faster. Strip looks cheaper per metre only because the masonry is priced separately.

Concrete delivery and pump hire, building control fees (£300–£1,000), masonry above strip footings, reinforcement, drainage pipework, sub-base and slabs, and labour beyond the machine dig. It also assumes normal ground — running sand, roots, old footings or a high water table all push real quotes up, and London prices run 15–25% higher.